IN 2022, SEVENTY-SEVEN (77) NEW WELLS WERE ADDED TO THE BAHRAIN FIELD. THESE WELLS WERE COMPLETED TARGETING RUBBLE, AHMADI, BAHRAIN, OST/MAG, FADHILI, MAUDDUD, KHARAIB AND KHUFF RESERVOIRS.
4. Production System Modelling
Significant milestones were completed on a number of projects in 2022 including:
DevelopinganintegratedFive(5)YearPlanfor the Khuff reservoir considering the paradigm shift from HP to LP operation (LP GDUs and compression) to prolong the lifetime of the reservoir. This included the GDN enhancement needed to accommodate additional gas requirements from Pre-Unayzah and LNG with a flexibility to operate at HP and LP.
Completing the GDN Enhancement Program (Phase 1) detailed engineering scope to debottleneck GDN by installing additional pipelines from AGS Jump Over to WVS. Procurement of materials is underway and the construction works have commenced for the onshore pipelines.
The detailed engineering activities are completed and procurement and construction works are in progress to install an additional pipeline between DDP and DMS to increase the capacity and to replace/bury the two (2) existing pipelines.