Facilities Engineering and Construction continued
40
Forty solar powered Continuous Demulsifier Injection (CDI) skids successfully installed
     Adding and burying of gas pipelines from DDP to DMS: The Project added an additional gas pipeline whilst burying the existing two (2) gas pipelines from Al Dur Distribution Point (DDP) to Al Dur Metering Station (DMS) to ensure continuous, redundant, and reliable gas supply to Al-Dur Power and Water Company (ADPWC). Successfully completed the mechanical works for the pipelines in 2022.
 LNG integration from AGS to DDP: The Project introduces two (2) new gas pipelines and two (2) new gas valve stations from Alba Gas Station (AGS) jump-over to Al Dur Distribution Point (DDP) to boost the integration of re-gasified liquefied natural gas (LNG) to the Bahrain Field. Phase 1 of the project is underway and Phase 2 will be executed by a future EPC Contract.
 GDN customer projects: Throughout the BAPCO Gas Station (BGS) project construction, Tatweer Petroleum had provided continuous support to the BMP team. Construction had commenced for BGS whilst all gas pipeline installation from Alba Distribution Point (ADP) and Riffa Distribution Point (RDP) up to BGS had been completed to ensure gas supply to the new BMP refinery.
Associated Gas (AG) and Oil Enhancement Projects
 Associated Gas Compressors: To satisfy the requirement of incremental field compression to support oil production, tendering process has been reinitiated in 2022 for AG Compression Phase VII to install an additional 105 MMSCFD compression capacity.
 Arab Gas Compression Phase II: To further offset the effect of declining Khuff gas reservoir pressure on the Arab reservoir production rate, the tendering process has been reinitiated in 2022 for Arab Gas Compression Phase II to install an incremental 25 MMSCFD compression capacity and the incremental gas injectors to maintain the oil production from Arab reservoir.
 New Well Manifolds: In line with the field development drilling program and to satisfy the requirement of incremental well production handling capacities to support oil production, a contract has been awarded in November 2021 to install two (2) additional Well Manifolds (WMs 32 and 33). Project execution is in progress where main engineering activities are completed and procurement is initiated for all major equipment and construction commenced in 2022.
 CDI Skids: Upon the successful installation of forty (40) solar powered Continuous Demulsifier Injection (CDI) skids in previous years, procurement was initiated for additional twenty (20) CDI skids to be installed in 2023.
 Gas Injection Conversions: As part of the Mauddud Tight Spacing Program, eight (8) wells from the Mauddud reservoir were converted to gas injectors in 2022. In addition, a total of eleven wells from different shallow reservoirs were also converted to gas injectors.
 Casing Vapor Recovery (CVR) Network: As part of the CVR developments in the Bahrain Field, the network was expanded to recover casing vapor gas from additional thirty-eight (38) wells in the Bahrain Field during the second quarter of the year.