 Power projects undertaken:
 Thirty-one (31) BPU conversions from hired power generator to permanent power supply (each generator feeding the BPU costs Tatweer Petroleum around US$ 22.5K/year).
 Second feeder installation for Mini-substation 02 11KV rings.
 Second feeder installation for to 33KV TB-01.
In 2022, the percentage of Preventive Maintenance (PM) to Corrective Maintenance (CM) ratio was PM 54% to CM 46 %, the fourth consecutive year in row for higher percentage of PM versus CM.
  Commenced AKWIRE application for scheduling of maintenance WO in the Mechanical and Shutdown and Field Services sections.
 Maintenance cost per barrel was US$ 3.43 for 2022 versus US$ 2.84 for 2021. However, this includes CS08/20 gas compression facility major breakdown works.
  125,264
Successfully completing all planned major maintenance shutdowns with a total of one hundred twenty-five thousand and two hundred sixty-four man-hours for turnarounds.
        PLANNED
Total Number of Work Orders (WO)
Total Actual Recorded Man Hours
% of Total Recorded Man Hours
    21,058 353,224 54%
17,741 300,356 46%
38,799 653,580 100%
   CORRECTIVE
  Total
   













































































   44   45   46   47   48