46 Tatweer Petroleum | Annual Report 2022 www.tatweerpetroleum.com
Field Maintenance
continued
Power projects undertaken:
Thirty-one (31) BPU conversions from hired power generator to permanent power supply (each generator feeding the BPU costs Tatweer Petroleum around US$ 22.5K/year).
Second feeder installation for Mini-substation 02 11KV rings.
Second feeder installation for to 33KV TB-01.
In 2022, the percentage of Preventive Maintenance (PM) to Corrective Maintenance (CM) ratio was PM 54% to CM 46 %, the fourth consecutive year in row for higher percentage of PM versus CM.
Commenced AKWIRE application for scheduling of maintenance WO in the Mechanical and Shutdown and Field Services sections.
Maintenance cost per barrel was US$ 3.43 for 2022 versus US$ 2.84 for 2021. However, this includes CS08/20 gas compression facility major breakdown works.
125,264
Successfully completing all planned major maintenance shutdowns with a total of one hundred twenty-five thousand and two hundred sixty-four man-hours for turnarounds.
PLANNED
Total Number of Work Orders (WO)
Total Actual Recorded Man Hours
% of Total Recorded Man Hours
21,058 353,224 54%
17,741 300,356 46%
38,799 653,580 100%
CORRECTIVE
Total