Page 51 - Tatweer AR 2022
P. 51

 Tatweer Petroleum | Annual Report 2022 51 www.tatweerpetroleum.com
IN 2022, SEVENTY-THREE (73) NEW OIL WELLS WERE ADDED TO THE BAHRAIN FIELD THAT CONSISTED OF FORTY-SIX (46) GAS LIFT WELLS AND TWENTY-SEVEN (27) BPUS.
   Rubble Phase 1 Acceleration Development: The Rubble Phase 1 Acceleration Development project was approved with the objective of maximizing steam utilization from the Rubble Steam Injection Plant (RSIP). Extensive engineering and procurement work were completed in 2022.
Well Development Program
In 2022, seventy-three (73) new oil wells were added to the Bahrain Field that consisted of forty-six (46) gas lift wells and twenty-seven (27) BPUs. In addition, there were sixty-eight (68) existing well production conversions and nineteen (19) existing well production conversions to gas injection GI wells, which included MGI, AGI and SGI wells that also contributed to the oil gain in 2022.
Facilities Improvement Projects
 Civil Projects:
 Construction of a new four (4) story office
building with canteen at Jabel progressed in 2022 as part of the approved Contract.
 ConstructionofReliefValvesStoreatJabel compound is underway.
 Upgrade power supply in Jabel compound project is initiated to support above projects and cover future power needs.
 Upgrade Oil Flow Lines Material (Phase IV): Reinforced Thermoplastic Pipes (RTP) is being used to replace carbon steel materials on a number of flow lines.
 Thirty-five (35) Oil Flow Lines (OFLs) were identified. Thirteen (13) were replaced and commissioned in December 2022 and remaining (22) lines are in progress and are expected to be completed in 2023.
 Four (4) MMFs were identified (Production/ Test lines). Two (2) MMFs lines were replaced and commissioned in December 2022 and two (2) are in progress.
 Two (2) WMs Oil Gathering Lines (OGLs) were identified/added to the project in October 2022. WM20 was completed in December 2022.
 WMs Booster Pump Improvements and Upgrades:
 Phase I: Mechanical modifications, instruments upgrade and process/logic enhancements at
six (6) new WMs progressed in 2022.
 Upgrade WM#3 Booster Pump: Project completed and commissioned in October 2022.
 Phase 2: Mechanical modifications, instruments upgrade and process/logic enhancements at four (4) legacy remote WMs is planned.
Design Section
 As-Building: As-Building of Critical Drawings for oil and gas production facilities was completed and new As-Building requirements were progressed during the year for any outstanding networks